NO | NAME OF CONTRACT | EMPLOYER | LOCATION | ORIGINAL CONTRACT DATE | COMPLETION DATE |
PROJECT LIST | |||||
1 | H4 KBR Headquarters Administrative Offices | Kellogg, Brown & Roots | Mosul, Iraq | 18.11.2004 | N/A |
2 | MWR Facility | Kellogg, Brown & Roots | Tallafar, Iraq | 19.11.2004 | 29.08.2005 |
3 | Operation of ready mix concrete batch plants | Oyak Beton | Mediteranean Region/Turkey | 01.01.2005 | 31.12.2005 |
4 | H4 CDC Building Warehouse | Kellogg, Brown & Roots | Mosul, Iraq | 11.02.2005 | 31.07.2006 |
5 | Procurement, Delivery & Installation of Living Containers | Kellogg, Brown & Roots | Mosul & Iraq | 19.02.2005 | 30.06.2006 |
6 | Construction of guard towers | Kellogg, Brown & Roots | Iraq | 01.03.2005 | N/A |
7 | Provision of Wet Concrete | II MEF Contracting Office, Camp Fellujah | Al Asad, Iraq | 10.03.2005 | 03.01.2006 |
8 | Concrete Slab at Add-On-Armor | Army, Mosul Regional Contracting Center | Mosul, Iraq | 25.05.2005 | N/A |
9 | Waste Water Treatment Ponds at H5 | Kellogg, Brown & Roots | Tallafar, Iraq | 23.07.2005 | 01.02.2006 |
10 | Provision, Transportation, Assembly & Setup of Two Man Living Containers | Kellogg, Brown & Roots | Tallafar, Iraq | 26.07.2005 | 21.01.2006 |
11 | Construction of Tank Wash / Bird Path | Kellogg, Brown & Roots | Tallafar, Iraq | 03.08.2005 | 18.01.2006 |
12 | Delivery and Installation of Jersey Barriers | Army, Mosul Regional Contracting Center | Tallafar, Iraq | 23.08.2005 | N/A |
13 | Delivery and Installation of Jersey Barriers | Army, Mosul Regional Contracting Center | Mosul, Iraq | 27.08.2005 | 10.09.2005 |
14 | Operations Building Refurbishment at FOB Marez | Army, Mosul Regional Contracting Center | Mosul, Iraq | 30.08.2005 | N/A |
15 | Delivery and Installation of T-Walls&Jersey Barriers | Army, Mosul Regional Contracting Center | Mosul & Tallafar, Iraq | 15.09.2005 | N/A |
16 | Construction of fence | USACE Gulf Region Division-Central District | Al Asad, Iraq | 20.09.2005 | 15.10.2006 |
17 | Multi-Use Building Refurbishment | Army, Mosul Regional Contracting Center | Tallafar, Iraq | 05.10.2005 | N/A |
18 | Force Protection Measures at Iraqi Air Terminal | FOB Courage Contracting Office | Mosul, Iraq | 05.10.2005 | N/A |
19 | Provision of an Office Tent Structure, a TMP building Tent Structure and a Concrete Slab for TMP Building Tent Structure on H5 | Kellogg, Brown & Roots | Tallafar, Iraq | 10.10.2005 | 30.05.2006 |
20 | Construct TMP Building on Pre-Existing Slab at H4 | Kellogg, Brown & Roots | Mosul, Iraq | 27.10.2005 | 29.09.2006 |
21 | Provision of Concrete Reinforced T-Walls | Kellogg, Brown & Roots | Tallafar, Iraq | 10.11.2005 | 15.04.2006 |
22 | Provision of Concrete Reinforced T-Walls | Kellogg, Brown & Roots | Mosul, Iraq | 10.11.2005 | 15.05.2006 |
23 | Provision, Transportation, Assembly & Setup/Install of Two Man Containerized Housing Units | Kellogg, Brown & Roots | Iraq | 06.12.2005 | 31.05.2006 |
24 | DFAC Dining Operations | Kellogg, Brown & Roots | Mosul & Tallafar, Iraq | 07.12.2005 | 30.09.2006 |
25 | 12' Interlocking T-Wall Concrete Barriers | Joint Contracting Command-Iraq Camp Fellujah | Al Asad, Iraq | 21.12.2005 | 11.03.2006 |
26 | Operation of ready mix concrete batch plants | Oyak Beton | Mediteranean Region/Turkey | 01.01.2006 | 31.12.2006 |
27 | Renovation of barracks | USACE Gulf Region Division-Central District | El Taqaddum, Iraq | 11.01.2006 | 25.09.2006 |
28 | Delivery and Installation of T-Walls&C-Bunkers | Army, Mosul Regional Contracting Center | Iraq | 15.01.2006 | N/A |
29 | Construction of TTM Area | Kellogg, Brown & Roots | Iraq | 06.03.2006 | 01.10.2006 |
30 | 12' Interlocking T-Wall Concrete Barriers | Joint Contracting Command-Iraq Camp Fellujah | Al Asad, Iraq | 20.05.2006 | 05.08.2006 |
31 | Runway repair | Joint Contracting Command-Iraq Camp Fellujah | El Taqaddum, Iraq | 01.08.2006 | 30.04.2007 |
32 | Construction of Concrete Medevac Parking Ramp | USACE Gulf Region Division-Central District | Al Asad, Iraq | 30.09.2006 | 12.12.2006 |
33 | Construction of High School | Ministry of Education | Adana, Turkey | 01.11.2006 | N/A |
34 | 30 CHUs for Habur Gate | Kellogg, Brown & Roots | Habur/Zakho, Iraq | 02.08.2007 | 31.10.2007 |
35 | IDIQ MATOC Construction | USACE Europe District | Incirlik, Turkey | 10.08.2007 | N/A |
36 | Construction of Electrical Infrastructure Upgrades | Kellogg, Brown & Roots | Al Asad, Iraq | 06.09.2007 | 12.03.2009 |
37 | Construction of Parallel Taxiway and Aprons in Bagram Airbase, Afghanistan | Kellogg, Brown & Roots | Bagram, Afghanistan | 19.03.2008 | 12.09.2009 |
38 | Operation of ready mix concrete batch plants* | Oyak Beton | Mediteranean Region/Turkey | 01.04.2008 | 31.12.2010 |
39 | GCA8YM-SO00141-Concrete Apron at CSC Yard on Site H3 | Kellogg, Brown & Roots | Iraq | 26.05.2008 | 30.11.2008 |
40 | Construction of TMC Expansion on Site H3 | Kellogg, Brown & Roots | Q-West, Iraq | 28.06.2008 | 31.01.2009 |
41 | Construction of Hydro Power Energy Plant | Laskar Enerji A.S (sister company) | Rize (İncirli HES), Turkey | 01.07.2008 | N/A |
42 | H3 Q-West Dental Clinic Construction | Kellogg, Brown & Roots | Q-West, Iraq | 08.10.2008 | 31.03.2009 |
43 | Supply of Reefer Containers | Bagram Joint Contracting Cell | Bagram, Afghanistan | 10.10.2008 | N/A |
44 | Supply of Reefer Containers | Bagram Joint Contracting Cell | Bagram, Afghanistan | 10.10.2008 | N/A |
45 | Supply of Insulation Cover | Bagram Joint Contracting Cell | Bagram, Afghanistan | 04.02.2009 | N/A |
46 | Supply of Insulation Cover | Bagram Joint Contracting Cell | Bagram, Afghanistan | 05.02.2009 | N/A |
47 | Bagram Concrete Barrier BPA | Bagram Joint Contracting Cell | Bagram, Afghanistan | 03.06.2009 | N/A |
48 | Bagram Bulk Fuel Storage and Supply | USACE Transatlantic Programs Center |
Bagram, Afghanistan | 18.06.2009 | 23.06.2011 |
49 | Supply and Laydown of Gravel | Fluor Intercontinental, Inc. | Bagram, Afghanistan | 22.09.2009 | N/A |
50 | Force Protection for Transition Sites at Bagram | Fluor Intercontinental, Inc. | Bagram, Afghanistan | 17.10.2009 | #BAŞV! |
51 | Warrior East - Supply and Install Fencing Project | Fluor Intercontinental, Inc. | Bagram, Afghanistan | 23.11.2009 | 12.12.2009 |
52 | Warrior Triangle - Supply and Install Fencing Project | Fluor Intercontinental, Inc. | Bagram, Afghanistan | 12.12.2009 | 03.01.2010 |
53 | Strategic Airlift Ramp & Hot Cargo Pad at Manas Airbase | USACE Transatlantic Programs Center |
Manas / Kyrgyzstan | 22.12.2009 | 21.06.2011 |
54 | AMC Concrete for FN Housing | Bagram Joint Contracting Cell | Bagram, Afghanistan | 29.12.2009 | 31.12.2009 |
55 | Diagnose and Repair Fire Alarm System | Kellogg, Brown & Roots | Al Asad, Iraq | 26.01.2010 | N/A |
56 | Supply and Deliver 12ft T-Wall Barrier | Army, Mosul Regional Contracting Center | Mosul, Iraq | 28.01.2010 | N/A |
57 | WARRIOR EAST - FLUOR CMO AND LSA | Fluor Intercontinental, Inc. | Bagram, Afghanistan | 10.03.2010 | N/A |
58 | Concrete West Side POL Concrete Pad | Department of the Air Force | Bagram, Afghanistan | 21.05.2010 | N/A |
59 | Alpha 17 Hot Cargo Pad | Department of the Air Force | Manas, Kyrgzstan | 27.08.2010 | N/A |
60 | Heavy Equipment Lease | Department of Defense | Manas, Kyrgzstan | 18.09.2010 | N/A |
61 | Rubber Removal and Paint Marking | Department of Defense | Manas, Kyrgzstan | 09.10.2010 | N/A |
62 | Potable Water Provision and Black Water Removal Services Kürecik, Malatya | US Army | Malatya, Turkey | 12.01.2011 | N/A |
63 | 20 Foot T-Wall, Iraq | Al Mubarak International LLC | Baghdad, Iraq | 18.04.2011 | N/A |
64 | Manas Concrete IDIQ- Task Order 1 TCA Sidewalks | Department Of Air Force | Bishkek / Kyrgyzstan | 08.09.2011 | N/A |
65 | Rubber Removal Painting Runway | USAF | Bishkek / Kyrgyzstan | 10.10.2011 | N/A |
66 | Design-Build Construction of JSS Shield in Baghdad, Iraq | U.S. Department of State (OBO) | Shield, Baghdad, Iraq | 12.04.2011 | 11.07.2012 |
67 | Border Crossing Facilities at Batken | USACE Middle East District | Batken, Kyrgzstan | 27.09.2010 | 25.12.2011 |
68 | Construction of Hydro Power Energy Plant | Boztepe Enerji A.S (sister company) | Adıyaman (Gemciler HES), Turkey | 19.07.2011 | 18.12.2012 |
69 | MATOC for design-build and construction projects US Central Command CENTCOM) Area of Responsibility TO #1: C-IED Task Force Compound | Kellogg, Brown & Roots | Bagram, Afghanistan | 06.07.2011 | N/A |
70 | FY11 Multiple Repair Projects for BCE, Turkey | US Army | Incirlik, Turkey Ankara, Turkey |
30.09.2011 | 31.07.2013 |
71 | Runway Repair, Bagram, Afghanistan | Anham-ICS Serka JV USACE |
Bagram, Afghanistan | 11.02.2013 | N/A |
72 | Baghdad Master Plan Implementation for Sather Air Base, Baghdad, Iraq. | U.S. Department of State (OBO) | Baghdad, Iraq | 16.02.2012 | 15.02.2014 |
73 | 2 ea Aviation Fuel Truck Lease at Kunduz, Afghanistan | Fluor Intercontinental, Inc. | Kunduz, Afghanistan | 06.01.2012 | 14.05.2014 |
74 | 2 ea Aviation Fuel Truck Lease at Marmal, Afghanistan | Fluor Intercontinental, Inc. | Marmal, Afghanistan | 18.08.2012 | 12.03.2014 |
75 | Construction of Hydro Power Energy Plant | Mertler Enerji A.S (sister company) | Rize (Saray HES) , Turkey | N/A | 16.07.2014 |
76 | Construction of 5* hotel | Serka Turizm ve Ticaret A.S. (sister company) | Adana, Turkey | 21.08.2008 | 28.05.2014 |
77 | Design/Build Repair Runw ay 08/26, Transit Center at Manas Manas, Kyrgyzstan | USACE Middle East District | Manas, Kyrgyzstan | 22.12.2011 | 31.07.2014 |
78 | Runway Repair, Bagram, Afghanistan | US Army Corps of Engineers | Bagram, Afghanistan | 11.02.2013 | N/A |
79 | ISAT Security Upgrades, Baku Embassy, Azerbaijan | U.S. Department of State (OBO) | Baku, Azerbaijan | 30.05.2013 | 12.05.2014 |
80 | Air Traffic Control Tower (ATCT) Design and Construction And WAM/VHF Equipment Installation | Raytheon | Manas / Kyrgyzstan | 06.10.2011 | On-going |
81 | Construction Services for FY10 OBC Compound Rehab Niamey, Niger | OBO | Niamey, Niger | 10.06.2011 | On-going |
82 | Drainage System, Phase 3, Bagram, Afghanistan (9 MATOC MED 3 2012) | Anham-ICS Serka JV USACE |
Bagram, Afghanistan | 15.08.2012 | On-going |
83 | Eastside Utilities Infrastructure, Bagram, Afghanistan | Anham-ICS Serka JV USACE |
Bagram, Afghanistan | 09.04.2012 | On-going |
84 | Freetown Rainwater Capture and Storage System | U.S. Department of State (OBO) | Republic of Sierra Leone | 03.09.2013 | On-going |
85 | Asphalt Road Repair at Bagram Airfield, Afghanistan | USACE - REGIONAL CONTRACTING CENTER-EAST | Bagram, Afghanistan | 16.09.2014 | On-going |
86 | Construction of Wind Power Energy Plant | Beşiktepe Enerji A.S (sister company) | Tekirdağ (Kıyıköy RES), Turkey | 01.09.2014 | On-going |